NPC News Bulletin
News Bulletin Home Page Published Issues Contact Us WWW.NIPC.NET
Check out published issues directly.

would you like to be informed when new issues of the news Bulletin becomes online?
Click here

Do you have any comments?
Click here



Fajr Petrochemical Co. (FPC), the NPC's wholly-owned centralized utility complex in Petrochemical Special Economic Zone in Bandar Imam is operational, delivering utilities to a host of petrochemical plants at the Zone. FPC is getting ready for official inauguration due to take place in the near future. Fajr consists of four units: a power plant, an air separation unit, a water treatment complex, an effluent treatment plant including an offsite facilities network.



The power plant produces 585MW of electricity and 830 tonne/hour of steam. The air separation plant produces 15,000 Nm3/hour of instrument air, 16,500 Nm3/hour of service air, 18,000 Nm3/hour of nitrogen and 19,000 Nm3/hour of oxygen. The water treatment plant purifies 7,000 m3/hour of water which it receives from the Karoon River providing 7,000 m3/hour of fire-fighting water, 400 m3/hour of service water, 250 m3/hour of potable water, 3,900 m3/hour of reverse osmoses (RO) water. The effluent treatment plant has a designed capacity of 460m3/h to treat and purify polluted waters, including oily polluted waters, chemical effluents and sanitary effluents.




Work has already started to expand Fajr. The engineering work for train-III of the air separation plant has been completed and piling work is in progress. Commissioning is scheduled for January 2005.
FPC expects to award a contract by 30 March 2004 for the supply of two other gas turbines (GT 6 & 7) with a capacity of approximately 255MW. The gas turbines are planned to be commissioned by November 2006.
Work is also under way to expand the capacity of the water treatment plant with commissioning envisioned for June 2006.
Meanwhile, offsite pipe rack and piping work for supplying utilities to all of the petrochemical facilities located at site 2, 3 and 5 of the Petrochemical Special Economic Zone is in progress. The work is slated for completion by December 2004.




NPC is planning to issue invitation-to-bid (ITB) documents to interested contractors for Fajr expansion which will be built in a 20-hectare area. FPC has already started the site grading activities. Ths expansion project will consist of an effluent treatment plant, a water treatment unit, an air separation facility and a power plant. The completion target for the effluent treatment plant is January '05. Completion dates for the water treatment, air separation and power plants are August, July and October 2006 respectively.



Fajr Key Highlights
Feed Amount Source
Raw water 7,000m3/h Karoon River
Natural gas 7mm3/d National grid
Volume of excavation/earth filling 450,000m3
Volume of concrete work 115,000m3
Weight of steel structure 11,942 tonnes
Weight of equipment 16,357 tonnes
Piping 509,200 inch-dia
Cabling 1,049km
Piling 229km
Engineering work 1,300,000 man/hour
Erection & construction 22,000,000 man/hour
Manpower during operation 260


Check Out
© 2000,NPC website All Right Reserved MIS Department of NPC |  Home  |   Published Issues   |   Contact us    |  NIPC.NET