Shahid Tondguyan Petrochemical Co. (STPC) and the local company Kanroodsaze Construction Co.
signed an agreement for civil, structure as well as mechanical and electrical installations for
PET-2 project industrial buildings. STPC is an NPC subsidiary responsible for implementing and
operating PET/PTA 1 and 2 at Bandar Imam Petrochemical Special Economic Zone. Duration of the
agreement is 12 months starting from 28 July 2002. An agreement for civil and mechanical
installations are also being drawn up for PTA-2 project. In mid July 2002, overall physical
progress for PTA/PET-2 project was over 28.2%. The progress included basic and detailed engineering,
procurement activities as well as site preparation, preloading, loading and piling.
Khuzestan Petrochemical Co. (KPC) expects that its bisphenol A (BPA), polycarbonate (PC) and epoxy resin
plants become operational in 2003. KPC, a subsidiary of NPC, is implementing an engineering polymers
project in Bandar Imam Petrochemical Special Economic Zone on the northern coast of the Persian Gulf.
In early July 2002, KPC set up a steering committee to oversee and direct commissioning activities.
It plans to kick off pre-commissioning work on its BPA plant in November 2002. The plant has an output
capacity of 30,000 tonne/year. The plant's reactors have already been installed. It is expected to
start commercial production in Q1 of 2003. Pre-commissioning work on KPC's 10,000 tonne/year epoxy
resin and 25,000 tonne/year PC projects are planned to start in early 2003. The two plants are anticipated
to be on track two to four months after pre-commissioning work is completed.
The contract for the construction of a petrochemical port in Assaluyeh was officially signed. NPC had awarded
the contract to the local firm Khatam-ol-Anbia Construction Group. The contract calls for detailed engineering,
procurement and construction. The Turkish company STFA has been named as the project's sub-contractor.
The first phase of the project is scheduled to be completed in 24 months while the entire project is expected
to be operational within 48 months. Construction work has already commenced on two breakwaters.
The port will be used for the export of material from production units currently under construction.
It will have an annual loading and unloading capacity of 27m-30m tonne of petrochemicals, including 5m-6m tonne
of solid products and 22m-24m tonne of liquid products. The facility will have 14 berths, which will be able to
accommodate ships up to 60,000 tonne deadweight.
NPC and South African major Sasol held more negotiations about possible partnership in a Gas-to-Liquids (GTL) project
and a polymer facility both located in south of Iran on the coast of the Persian Gulf. A joint feasibility study for
the polymer facility is expected to be completed by September 2002. NPC and Sasol concluded a joint pre-feasibility study
for the GTL project. Both studies have unfolded promising results. The GTL project forms part of NPC's plan to develop
environment-friendly products in Iran.